Electrical Panel Permits and Inspections in Dallas, Mesquite, Garland and Rowlett
The short version
- A permit is pulled before work starts.
- The utility disconnects and reconnects your power. Only the utility removes the meter or breaks its seal.
- A city inspector checks the finished work.
- In most cases, the utility reconnects after the city clears the job.
- Permit fees are set by each city. Ours are included in the written quote.
Who pulls the permit
Cities handle this differently. Dallas, for example, has published a homeowner permit process that requires proof of homestead and plans filed with the city. Some Texas cities exclude main service work from homeowner permits altogether.
What happens, step by step
1. Site check and quote
2. Permit
3. Utility disconnect request
4. Work day
5. Inspection
6. Clearance and reconnect
Oncor and Garland Power & Light: what changes
Most homes in Dallas, Mesquite, and Rowlett get their delivery service from Oncor. Most Garland homes are served by Garland Power & Light (GPL), a city-run utility, and some Garland addresses are served by Oncor. Zip codes in Garland can be split between the two, so your electric bill is the quickest way to tell.
The process looks similar either way: a disconnect, the work, an inspection, a reconnect. The difference is in the details, like which office takes the request, what the utility requires for the meter socket and mast, and how the city’s inspection result gets to the utility. Ask your electrician which utility serves your address and how they handle that utility’s process. If the answer is vague, that’s worth noticing.
What the inspector checks
Working space
Panel location
Grounding electrode system
Neutral and ground connections
Breakers and wire sizes
AFCI and GFCI protection
Surge protection
NEC 230.67 requires a Type 1 or Type 2 surge protective device on services that supply dwelling units, installed as part of the service equipment or immediately adjacent to it. It applies when service equipment is replaced, so it’s part of a panel replacement. We cover this in our whole-home surge protection guide.
Labeling
Service entrance equipment
The meter socket, mast, and weatherhead need to be secure, weatherproof, and installed to the utility’s requirements, including clearances and the drip loop. Our meter socket page covers the common failures.
Common reasons an inspection fails
- Panel directory missing or unreadable
- No surge protective device
- Clearance in front of the panel blocked
- Neutral and ground bonded in a subpanel
- Double-tapped breakers, or a breaker not listed for that panel
- Open knockouts, missing cable clamps, or cables without proper protection where they enter the panel
- Loose connections or terminals not torqued to spec
- Grounding conductors undersized, or clamps buried or inaccessible
- Meter socket, mast, or weatherhead not meeting the utility's specification
Most of these are quick to correct. Each one costs a re-inspection and a delay, and some cities charge for repeat visits.
What skipping the permit can cost you
- The utility may not reconnect. If the work involved a meter pull or service change without city clearance, the utility can hold the reconnect until the city is satisfied.
- A stop-work order or fine. Cities enforce permit rules, and the cost of a fix after the fact is usually higher than the permit.
- Trouble when you sell. Buyers' inspectors and agents ask about permits, and an unpermitted panel can stall a closing until it's resolved.
- Insurance questions. If there's a fire or electrical claim, an insurer may look closely at unpermitted work. Policies differ, so ask your insurer how it treats it.
- Nobody verified the grounding. The inspection is the only independent check that the safety-critical parts of the job were done right.
What it costs
For the full price picture, see our 200-amp panel upgrade cost guide.
Questions to ask before you hire an electrician
- Can I see your license on the TDLR license search, and is the permit pulled in your company’s name?
- Who requests the utility disconnect and reconnect, and what happens if the utility’s schedule slips?
- Is a surge protective device included in the quote?
- Does the quote include the meter socket and mast if they need work, or is that an add-on?
- What happens if the inspection fails, and who pays for the re-inspection?
- Will I get a copy of the permit and the passed inspection?
Frequently asked questions
It depends on your city. Texas exempts owner-occupants from electrician licensing, but cities can require permits, limit what homeowners can do, or exclude main service work. Dallas has a published homeowner permit process. Check with your city before assuming. We recommend a licensed electrician for any work involving the main service.
It varies by city and by how the application is filed. Ask the city or your electrician for a current estimate.
Often, but not guaranteed. It depends on when the utility disconnects, how long the work takes, and when the inspector is available.
No. An inspection checks the main code items on the day of the visit. It’s a safety check, not a warranty. That’s why who does the work matters as much as the permit.